PB July-August 2023 July-August 2023 21
T
his article looks at whether the
already dysfunctional and long-
delayed Metro risks further
disruption by the illegal and pre-
emptive choice of an inappropriate
terminus, at Charlemont, for the crucial
interchange between the underground metro
and other modes of transport on the south side.
Dublin’s delayed and
diminished Metro
In 2019, the National Transport Authority (NTA)
shelved plans for the southernmost leg of
Dublin’s Metro. Originally a 26-km fully-
segregated Metro Link rail line had been due to
open in 2027.
Now the plan is for construction, 2025-35, of
a railway approximately 18.8km in length,
12km underground, punctuated by 16 new
underground stations as well as existing Luas
stops. It will include 9.4km and 2.3km sections
of single-bore tunnel running beneath Dublin
City Centre and Dublin Airport, respectively.The
Charlemont
Charlatanism
Dublins proposed
Metro is an unplanned
mistake, facilitated by
egregious procedural
and consultation
failures over
Charlemont station,
that risk derailing it
By Mannix Flynn
NEWS
journey time will be 25 minutes from Swords to
Charlemont, and it is envisaged that frequency
of trains will be every three minutes at peak
time carrying up to 20,000 passengers in each
direction per hour.
But why stop at Charlemont of
all places?
The sole aim of the only study carried out by the
NTA before they revised their capacity forecast
was to identify where a “tie-in”, a link between
transport modes, should go. Despite becoming
a totally dierent project, the NTA are hell-bent
on sticking rigidly to their original plan to
replace the Luas Green line with an above-
ground, segregated, driverless Metro rather
than, for example, being underground.
It seems, for good or bad, they are trying to
create facts on the ground so an unapproved
decision can never be undone.
In early June, the Secretary General of the
Department of Transport, Ken Spratt, told the
Public Accounts Committee that the spend on
the MetroLink project to the end of March of
this year was €115.3 million — in addition to the
166 million spent on the Metro North project
the last of which was spent in 2014. The
envisaged total cost at the moment is €9.5bn,
though “probable” ranges are €7.2bn to
12.3bn. An extraordinary €.44bn is predicted
in “base land and property” costs, for lucky
landowners, for the most part over an
underground.
Critical connection
NTA chief executive Anne Graham said the
Metrolink could not terminate at St Stephen’s
Green as it would be disruptive to commuters
who were seeking to use the Luas to continue
their journey. The case, however, has not been
made.
It’s on the east side of Stephen’s Green,
that’s where the metro station is proposed to
be, rather than the current west side where the
green line operates currently, she said.
Charlemont was chosen for the terminus as
it provides more options for future planning,
she added. Presumably the reason the site on
Charlemont is even being considered for the
terminus is as its a rare site undergoing new
22 July-August 2023 July-August 2023 23
development along the former Harcourt St Line
close-ish to the city centre. We don’t know this
for certain of course - because the process to
explain whats going on is deficient.
But there are major logistical problems with
Charlemont too: drawings issued for the
Charlemont Metro Station show two lines
about 200 metres apart, one below ground and
one on a bridge.
They are connected by three flights of
escalators, a walk in the open and three flights
of two-way steps. It will not achieve the
“seamlessness” touted by the Quixotic NTA.
Business case and Railway
Order still pending
A “preliminary” business case cornily titled
‘Integrated Transport. Integrated Life’ was
submitted to the Cabinet in September 2022
and was followed by an application for a
Railway Order toAn Bord Pleanála, consultation
on which ended in January 2023.
Works are premature and
unlawful
Yet work was afoot as long as a year ago, with
the NTA already implementing their original
plan, which will include an inevitable €2.5bn
public-private partnership, though this as
always will inevitably work to the
disproportionate benefit of the private; and
creating serious, dicult-to-reverse activity on
the ground. The point of planning is to avoid
this.
Let’s see whats happening.
Hines’ development at Grand
Parade, Charlemont
In March 2017, Hines, one of the biggest US
developers currently building Ireland’s biggest
construction scheme at Cherrywood, submitted
a planning application to Dublin City Council
(DCC) for an oce development right on the
preferred option for the Luas “tie-in” location.
The development is be called 2 Grand Parade,
and it embraces the significant modernist
protected structure, the old Carroll’s Cigarettes
building, later the headquarters of dodgy Irish
Nationwide Building Society. It also included
the construction of a new multi-storey oce
block.
NTA and TII concerned so seek
pre-development agreement
from developer
The NTA and Transportation Infrastructure
Ireland (TII) immediately raised concerns about
the impact of the development on the existing
Luas and on future Metro proposals and asked
Hines to “consult with the NTA in regard to the
development proposal with the future delivery
of New Metro North and its extension to Metro
South”. DCC’s permission included the
following condition:
“Prior to commencement of development,
the developer shall enter into an agreement
with TII/ NTA…to accommodate the potential
development, construction and operation of a
metro or light railway on, at, or near the site of
the approved development.
So far so good; but what happened next is of
very serious concern.
The agreement the NTA sought from Hines
was not merely to “accommodate the potential
development” of a Metro station but was to get
them to actually build the foundations for it
before it was ever approved. These “enabling
works” would create the “exoskeleton” box or
framework for the ultimate station.
Substantial station works now
completed
Enabling works are works that make the site
ready for construction works. That is not what
we have seen at Charlemont: for a start a box
is not a preparation but an actual work of
construction. Furthermore the works have cost
12.5m up to 2022. The station box required
the construction of a concrete ‘slab’ that rests
on the piled walls and forms the roof of the
station. This necessitated two overnight
concrete pours (continuous 16 hours - 8pm to
12 noon) to construct the unusually thick (and
expensive) slab of 2.6m specified by the station
architects, who want to preserve the aesthetic
of an underground station without any visible
pillars. The durable specification hardly meets
the prescription of “enabling works”.
Between Hines and the authorities they
decided that the public were not to be told that
Metro infrastructure was being built.
What should have happened, to follow the
precedent from 2008 of similar enabling works
carried out under the new Mater Hospital for
the (shelved) Metro North project, is that the
NTA would: secure Ministerial approval to do
the enabling works; secure a specific
construction budget, separate from the budget
designated for the submission for the Metro
Railway Order planning application; wait to
construct the enabling works only after the
Railway Order was approved by ABP; and follow
EU procurement procedures in tendering for the
construction of the enabling works.
Instead, the NTA took the decision to proceed
with the Charlemont works themselves and did
not ask the Minister, did not secure a specific
budget but used other funds (presumably
those earmarked for the Railway Order
application but not for construction), did not
wait for the democratic process of the granting
of a Railway Order, and did not engage in EU
procurement procedures.
Not only did the NTA not follow proper
procedure and precedent, it arranged for
construction of railway components that had
no permission of any standing in law. That is, it
forced through the construction of the
foundations of its desired Charlemont metro
station, unlawfully.
The NTA claims that Hines secured valid
planning permission on its behalf. But Hines’
permission for its oce block was granted
under the Planning and Development Act 2000
which expressly excludes permission for
“railway works”. It is, therefore, impossible for
Hines to have obtained valid permission.
The fundamental fact is that the NTA
subverted the prescribed process, procedures,
precedent and law in order to get its desired
station built – before a more appropriate
process might adjudicate another site as more
suitable.
In early 2022, the station box works were
complete and Hines finally began the
construction of its oce building.
A spokesman for TII confirmed that Hines
undertook enabling work. “Under the
agreement the State will fund the cost of the
enabling works [approximately €12.5 million]
and will reimburse Hines for the works when
completed”. It is not clear which government
agency has funded this unlawful commitment.
The Mn: Owen Keegn, Dublin City Chief
Executive
Residents, many affluent, in one of the
richest and most elegant parts of Dublin 6,
wonder whether the area is really the best
place for a city-centre terminus for the next
25 to 30 years
22 July-August 2023 July-August 2023 23
The delinquent authorities have benefited
from the support of the likes of the Dublin
Commuter Coalition which asserted that the
works are merely “enabling”.
Pre-commencement
agreement required
City Chief Executive, Owen Keegan, places a lot
of store on delivery of the Bord Pleanála
requirement that, prior to commencement of
the oce building, the developer shall enter
into the agreement with the NTA and TII.
It is not clear whether it was envisaged, or
legally required, that such agreement be
subjected to planning approval.
And the condition seems to contemplate
reaching of that agreement before planning
permission has been sought for the line the
station would serve! It is a grotesque
subversion of the logic of planning.
And that’s parking the issue that it should
have been applied for as a Railway Order not a
planning permission!
Substantial risk to the overall
MetroLink project
The circumstances under which the NTA
reached such an agreement with Hines and the
fact that works have already been completed
at a cost of at least €12.5m, pose a very
substantial risk to the overall MetroLink
project. It appears likely that the 40 south
Dublin residents’ associations, which have
called for the line to terminate at a city-centre
location such as St Stephen’s Green, will
robustly challenge the legality of the NTA’s
actions.
It seems unlikely that a court would find that
circumventing the planning system by a cosy
internal agreement was lawful. Still less is it
likely the internal agreement would preclude
compliance with other parallel regimes such as
that of Railway Orders.
Only when NTA/TII obtain full planning
permission to construct part or all of a Metro
station, can they reach an agreement with
Hines to build a station box on NTA/TII’s
behalf.
The NTA seems to be ignoring the strictures
that you would expect the largest
infrastructure project in the history of the
state to adhere to, namely:
Compliance with Railway and Planning Law;
Compliance with EU law on environmental
impact assessments including its
requirement of public consultation;
Procurement Law. Station works should be
put out to fair tender under EU procurement
law;
Proper use of funds. The NTA has a budget
to prepare a Railway Order Application not a
budget to construct infrastructure in advance
of even a business-case sign-o;
Ministerial approval.
Costly duplication of
Infrastructure and a lock-in for
the NTA’s preferred route
The NTA Metro proposal will duplicate the Luas
Green Line for the section from St Stephen’s
Green to Charlemont; i.e. while we are waiting
for the predicted post-2042 capacity issues to
be addressed, the Luas line and Metro line will
both be running. The cost of this duplication is
expected to be around €500m for tunnel
excavation but more especially Charlemont
station build-out. It will only be recoverable if
the infrastructure is re-used after 2042. The
NTA’s own feasibility studies state that the two
alternative potential Metro-extension routes to
the south west (which badly needs new
transport infrastructure) and south central via
UCD are not viable. Therefore, if a station at
Charlemont is built the only way to get a return
on the €500m duplication of rail infrastructure
is to replace the Green Line Luas post-2042.
This will be a de facto lock-in of the NTA’s
original preferred route. This is why the NTA are
going to such extraordinary lengths to ensure
it can get Charlemont built.
Many argue that a terminus at
Charlemont is misplaced
Residents, many auent, in one of the richest
and most elegant parts of Dublin 6, wonder
whether the area is really the best place for a
city-centre terminus for the next 25 to 30 years.
The solution they propose is build a shorter
route, with one less station and adapt the St
Stephen’s Green station into a proper City
Centre Terminus. They argue that this will save
the taxpayer hundreds of millions of Euros.
I believe a judicial review of the aair is in
order and there should be an investigation into
then Deputy Council City Planner Mary Conway,
and her superiors, who handled the débacle.
For and against Charlemont as
site for terminus
Residents groups argue against a Charlemont
terminus for the following reasons:
It would compound already huge trac
congestion which often develops along the
existing trac black spot at Portobello on
the canal.
It is intrinsically an inappropriate site for a
major Terminus being land-locked on three
sides with the canal on the fourth side.
It would provide a poor interchange from the
Luas – entailing a 400m walk from above-
ground Luas to below-ground Metro
It would provide poor transport connections
because of poor access for buses, taxis and
cars, and indeed poor local car-parking and
disability access.
Terminating at Charlemont would lock in the
Green Line replacement as the only viable
future Metro South Route – yet no decision
on Metro South is ocially being made now.
Charlemont is inappropriately far south
limiting the scope to bring Metro to key
densely populated areas eg Rathmines,
Knocklyon, UCD.
On the other hand the NTA emphasises the
proximity of the interchange at Charlemont
between the Luas and the MetroLink, much
closer than would be the case at St Stephen’s
Green. It also believes future extension options
from Charlemont are attractive.
As always with planning, it is important to
distinguish process from substance. The
former planner who facilitated the mistreatment
of the scheme under the Planning Act, an abuse
of the public’s right to consultation as well as
a possibly expensive strategic transportation
mistake, and the Chief Executive of DCC, who
grounded and justified it, need to consider
their positions for egregious failures under
both.
New office development t “tie in” djoins
the former Crroll’s building
Gerrd Mnnix Flynn is n independent Dublin
City Councillor for the South Est Inner City
which includes the Chrlemont re.