
36 April-May 2025
call that rational. Someone else might say that
it represents a deeply skewed set of values and
an unwillingness to face new realities”.
The judge pointed to a strengthening of the
wording of the section of the 2015 Climate Act
in the amending 2021 Act, which he described
as a foundational “step-change” from a ‘have-
regard-to’ to a ‘comply-with’ obligation. The
change followed the landmark judgment in
Friends of the Irish Environment v Government
of Ireland, which required greater specificity
within the government’s plans to achieve its
climate targets,
Under the 2021 Climate Act, An Bord
Pleanála, and indeed all public bodies
established under statute have to act
consistently with the government’s Climate
Plan, now in its 2024 iteration. But that’s on the
face of the Act so it is hardly surprising
Humphreys would apply it. However, in a
lengthy legal survey he then confoundingly
equates “consistent with” with “complying
with as”. But consistency means harmony with,
not obligation. Moreover both standards are
mitigated by the notion of “practicability”,
posing another layer of ambiguity.
Clarifying the context, he went on: “where
the obligation on the Board under section 15
to act ‘consistently’, insofar as practicable,
with the Climate Plans and Objectives is more
stringent than the obligation on the Board
under section 37G(2)(c) of the Planning and
Development Act to ‘consider’ the provisions
of the Development Plan, the Board was
required to exercise its discretion under
section 37G(6) to materially contravene the
Development Plan, unless it was not
practicable for it to do so. The Board therefore
erred in law and acted contrary to section 15 of
the 2015 Act in refusing permission for the
Windfarm Development on the sole basis that
it materially contravened the Development
Plan”.
The failure, he said, also constituted a
breach of duty under EU law and the European
Convention on Human Rights.
He ruled that “The board must ask itself
what substantive disposition of the matter that
is practicably available would contribute to
achieving the section 15 goals. In the case of
renewable energy projects, the answer to that
will almost always be a grant of permission,
and is obviously so here. It is not an answer
that the permitting of any one project won’t
achieve climate goals on its own. That is the
drop-in-the-ocean fallacy that is rejected
globally”. But it does not seem literally obvious
that without this wind farm the County Council
would, necessarily, not meet its renewable
targets and he relies in part on the “cumulative”
eect of ABP making similar decisions. His
forceful ruling denying the Bord has discretion
to refuse in this case and more generally for
windfarms “unless it is precluded by a
mandatory and non-fixable legal requirement”
may not stand up in the appeal that ABP is now
taking.
Central to Humphreys’ judgment was that:
“The obligation imposed by section 15 of
the 2015 Act on the Board is not delegable and
the Board had to perform, and to give
consideration as to how to perform, its
functions consistently with the Climate Plans
and Objectives, regardless of what steps had
or had not been taken by the Oce of the
Planning Regulator (OPR) and the Minister…It
is true at one level that, in a situation where
legally binding targets for renewables are not
actually being met, attempts by councils to
preclude or limit renewable energy
infrastructure can generally be regarded as
unlawfully inconsistent with EU, ECHR and
national law and policy in this area. But the fact
that the Oce of the Planning Regulation
(OPR) and the Minister for Housing, Local
Government and Heritage (the Minister) failed
to take any action to address the inconsistency
(something that the Climate Change Advisory
Council suggests they should urgently rectify
across the board) – especially I might add
given the relative triviality of some of their
objections to development plans in relation to
other matters…doesn’t make the refusal of an
application for such infrastructure consistent
with climate plans and goals when it wouldn’t
otherwise be so.
Refusing permission for the Proposed
Windfarm was inconsistent with the
achievement of the targets set by the 2024
Climate Action Plan of achieving 9GW of
onshore wind and an 80% share of renewable
electricity by 2030. In those circumstances, the
Board was required to grant permission for the
Proposed Windfarm, unless it determined that
it was not practicable for it to do so”.
This judgment is strong on rhetoric and
badinage, opening with an appropriate quote
from Bismarck and occasionally vituperating.
For example he asserts: “the board [which
followed its inspectors mistaken treatment of
the application as if it was an appeal] has to be
able to do better than fly on automatic pilot and
copy-and-paste mistakes into its decision-
making documents”.
Excitingly for radical environmentalists he
notes of climate: “The problem is that the
problem is so big that to even describe it
factually sounds like scaremongering”. He
accuses the board of raising “the petrified cry”
against any “far-reaching” interpretation of the
new terms in the 2021 Act. But, he says, “that
term isn’t the insult the board seems to think it
is”. He accuses ABP of “sabotaging” the
government’s climate commitments and refers
to its recent...diculties.
It is good to see an intelligent awareness of
the acuteness of the realities and imperatives.
Nevertheless, ultimately it does not work for
judges to strain the bounds of the law as they
are vulnerable to being overturned on appeal
which has an unfortunate chastening eect on
their future judgments.
Some weeks later on 7 February, in a more
important case, Friends of the Irish Environment
v the Minister for the Environment, Judge
Humphreys refused a judicial review of the
Climate Action Plan 2023. He determined that
the plan did provide quantifiable measures
and a level of specificity that would enable a
reasonable person to assess its likelihood of
meeting statutory objectives. The court
emphasised that the plan must ensure
compliance with carbon budgets and sectoral
ceilings, which involves quantification of
measures and estimation where necessary.
And he gave the applicants a flea in their ear
for not providing evidence of any lack of clarity.
Evidentiary reasoning, the narrowest
basis, can be a mark of reactionary decision-
making.
Refusing permission for the proposed Windfarm was
inconsistent with the achievement of the targets
set by the 2024 Climate Action Plan of achieving 9
GW of onshore wind and an 80% share of renewable
electricity by 2030. In those circumstances, the Board
was required to grant permission for the Proposed
Windfarm, unless it determined that it was not
practicable for it to do so